Utility construction underway in North Houston Heights

EAST ALDINE Management District iscontinuing their work on water and sewer lines, as construction has started on the North Houston Heights project. Photos show work on Collins Street, that began in October and is progressing.

The project is scheduled to take about 12 months, and includes new water lines, sewer lines, and a lift station. The contract was awarded to Calco, Inc. one of 6 bidders, for about $3.7 million dollars, and is being monitored by WaterEngineers, Inc. for Harris County and the Management District. A meeting with community residents was held on October 30th, to inform them how they can connect with the new systems.

Any additional questions can be directed to the Director of Services, Richard Cantu, and the EAMD offices, 281-449-1800. The project is near East Mt. Houston and the Orange Grove Elementary School.